Sol 23 FIDO Field Test Mission Manager Report
Jim Erickson
State from Sol 22
- The rover is in good health, and all functionality is available. Power
is still available to keep the Mini-TES warm and alive provided UHF
transmission is limited.
- This is a 70m antenna Sol. DTE this Sol is 11.06 megabits, UHF is
limited to a total of 24.5 megabits. Data remaining on board is 5 Megabits
from previous Sols
Sol 23 is an Approach Sol:
The mission manager is contemplating allowing a reduction in the
engineering data rate to increase the DTE available on these remaining end
of mission Sols. This will depend on the health of the vehicle and will be
decided on a Sol by Sol basis.
This Sol's main objective is to drive to a target called Black Lab and
attempt to position the rover to permit IDD operations on the target on Sol
24 or 25.
Sequence Development:
- After consultation with the Test Director, the flight rule limiting us
to a maximum 3.0m drive without hazard avoidance on is being waived by the
Mission Manager for this Sol. The rationale is that we are towards the end
of the mission, power is rapidly decreasing, we have a significant amount
of history with this rover's drive ability, and the engineering consensus
is that there is high confidence that there are no hazards anywhere in the
conceivable path of the vehicle even with a major discrepancy in the
actual versus predicted rover path.
- We sequenced a 3.3m traverse to a position approximately 1.02m away
from Black Lab. There will be a 50% chance that we will be in the IDD
workspace after this drive. Our expectation is that there would be a
further 95% chance of a traverse on Sol 24 getting us within the IDD
workspace.
- The uplink was approved with 8 minutes to go.
Sol 24 Considerations:
- First and foremost,did we succeed with the approach? If not, respond
to what we failed to do. Also evaluate the success of the direct drive of
over 3.0m (i.e., the flight rule waiver results).
Cumulative Comments:
- It is important for the theme groups to sequence their requested
observations, and in particular they should sequence their highest
priority observations first. On Sol 15, the highest priority Pancam was
not sequenced by the theme group, but the second and third were.
- Given extra time during sequence development, it is worthwhile to
review the science priorities as well as to review, in sequence order, the
visualizations of the image and remote spectroscopy requests.
- The modeling for IPS points needs to be updated. Ground testing should
be performed to determine the duration of IPS measurements as a function
of coadds. In addition, the modeling for Navcam images needs to be
updated, since they appear to take up twice as much space in the resource
modeling as they should at 16:1 image compression after a 12:8 pixel
compression.
- The tools do not provide a means to determine the actual length of
planned traverse segments. Furthermore, there are no good estimates with
uncertainty of the meters per minute that the rover (with hazard avoidance
on) can traverse as a function of the terrain type. Finally, there is
limited information on the dead reckoning capability of the rover on gyros
with respect to heading errors. Overall, there was no way to estimate the
traverse duration or error based on the traverse design and terrain
expectations, other than the experience of spacecraft team eyeballing the
situation. This would not be acceptable in a real mission.
- We need to request a change control board to adjust the Hazcam data
volume in the command dictionary from 2.1 to 1.05 Mbits.
- Clarification from PI: we have a mission success location if a) use
two out of three in situ instruments, and b) the PI is willing to advocate
that the science is new and different enough to make it a location.
- We need a ruling from the test director on whether we need Hazcam from
one meter back and Hazcam at the current location in order to perform an
arm operation. This may be affected by FIDO's ability to implement a stop
one meter short after a long traverse. If not, we may not ever be able to
do targets of opportunity after a long traverse.
- We have a test director flight rule to not use approach moves (hazard
avoidance off) for total moves of more than three meters. Note that this
is a Flight Rule that can be waived per Mission Manager (and has been on
Sol 23).
- Before this Sol, we have completed the requirement for 3 locations,
one trench (actually two), and have driven approximately 199 meters. After
this Sol, we will have traversed approximately 202.2m. There are three
Sols left.
Special Notes:
- Starting on Sol 16 and on all subsequent sols, the afternoon sol will
begin at 12:15 PM with all subsequent events shifting later by 15 minutes.
Updated sequence development schedule starting at 0900 and 1415:
- 70 minute Sequence Design
- 10 minute Sequence Validation
- 10 minute Sequence Approval
|