|
Sol 17 FIDO Field Test Mission Manager Report
Mark Adler
State from Sol 16
- Rover is in good health, and all functionality is available.
- The rover completed the planned traverse. The total odometry was 70.76
meters and the direct distance from the starting point is about 45 to 46
meters. The rover is level to within about 3°. Rover absolute heading
according to the engineers is within 10° of correct. According to the
atmospheres group, the heading is about 40° off based on a rear hazcam. We
need to resolve that discrepancy. The final Sun-find was not executed,
apparently due to field problems. The sequence appears to have been paused
due to some field interruption, and so the Sun may not have been in the
predicted position at the completion of the traverse.
- The test director ruled on the issue of absolute heading, and the
mission manager does not need to establish the absolute heading with
measurements every Sol in order to continue to receive DTE. The test
director will work the issue with the field.
- The test director ruled on the image volume issue, and we are
permitted to bookkeep the Hazcams at 1.05 Mbits as opposed to the current
2.1 Mbits. However we cannot modify the software to do that, and will have
to account for it manually. This may require a longer validation phase
during sequence development.
Sol 17 is an Approach Sol:
- At start of SOWG meeting, the chair requested one surface mini-TES on
Mini-tes1, five atmosphere mini-TES space two minutes apart to look for
turbulence.
- This Sol will be a drive to a trenching site, white1: nine meters to a
get close-up Navcam and Pancam of the trenching site, and then one meter
to the trenching site, followed by Navcam and Hazcam (Hazcam must be on
DTE to target trench point). The next Sol will be the trench and possible
IDD activity.
- The test director ruled that compressed sky images are permitted, but
again we will have to account for the data volume reduction manually.
Sequence Development:
- We started significantly over-subscribed in FIDO time. Arm activity
was deleted. A large Pancam mosaic at the end was deleted. Several IPS
observations were deleted. The cloud movie was shortened to three images.
The final sequence almost exactly filled the FIDO time and DTE. As usual,
the UHF was less than half subscribed. Much of the time in sequence design
was spent deleting and shrinking activities to get the sequence to fit. Do
to many modifications, the mission manager requested an extra validation
to make sure that the turns and approaches were correct, that the IPS
power on and off commands were correct, that the mast deploy and stow
commands were correct, and that the UHF and DTE commands were correct.
- A "blind" IPS observation was attempted, with the understanding that
the targetted terrain is relatively homogeneous so that precise pointing
was not necessary. Naturally, the actual pointing will be documented by a
Navcam wedge.
- 2.1 megabits were added to the DTE allocation to correctly account
manually for the two Hazcam pairs on DTE.
- The uplink was approved with three minutes to go.
Sol 18 Considerations:
- Sol 18 is a low DTE day, again about 4.1 Mbits. Adjust contingency
sequence data volumes if necessary to obtain DTE contingency data.
- Determine the trenching target. See if UHF contains information needed
to support traverse on Sol 19. The mission manager will need to decide
whether a traverse after trenching is allowed with older Navcam data. We
won't have enough DTE to get Navcam data from the new position.
Cumulative Comments:
- It is important for the theme groups to sequence their requested
observations, and in particular they should sequence their highest
priority observations first. On Sol 15, the highest priority Pancam was
not sequenced by the theme group, but the second and third were.
- Given extra time during sequence development, it is worthwhile to
review the science priorities as well as to review, in sequence order, the
visualizations of the image and remote spectroscopy requests.
- The modeling for IPS points needs to be updated. Ground testing should
be performed to determine the duration of IPS measurements as a function
of coadds. In addition, the modeling for Navcam images needs to be
updated, since they appear to take up twice as much space in the resource
modeling as they should at 16:1 image compression after a 12:8 pixel
compression.
- The tools do not provide a means to determine the actual length of
planned traverse segments. Furthermore, there are no good estimates with
uncertainty of the meters per minute that the rover (with hazard avoidance
on) can traverse as a function of the terrain type. Finally, there is
limited information on the dead reckoning capability of the rover on gyros
with respect to heading errors. Overall, there was no way to estimate the
traverse duration or error based on the traverse design and terrain
expectations, other than the experience of spacecraft team eyeballing the
situation. This would not be acceptable in a real mission.
- We need to request a change control board to adjust the Hazcam data
volume in the command dictionary from 2.1 to 1.05 Mbits.
- Clarification from PI: we have a mission success location if a) use
two out of three in situ instruments, and b) the PI is willing to advocate
that the science is new and different enough to make it a location.
- We need a ruling from the test director on whether we need Hazcam from
one meter back and Hazcam at the current location in order to perform an
arm operation. This may be affected by FIDO's ability to implement a stop
one meter short after a long traverse. If not, we may not ever be able to
do targets of opportunity after a long traverse.
- Before this Sol, we are at 2 out of 3 locations, zero trenches, and
approximately 130 meters. We in the unusual position of being ahead of our
mission success criteria!
Special Notes:
- Starting on Sol 16 and on all subsequent sols, the afternoon sol will
begin at 12:15 PM with all subsequent events shifting later by 15 minutes.
Updated sequence development schedule starting at 0900 and 1415:
- 70 minute Sequence Design
- 10 minute Sequence Validation
- 10 minute Sequence Approval
|