|
Sol 12 FIDO Field Test Mission Manager Report
Mark Adler
State from Sol 11:
- The DTE session was interrupted by wind problems, and the DSN antenna
was stowed. Nevertheless, the most critical Hazcam images from the middle
and the end of the traverse were received. That was sufficient to
determine that the approach was successful, and rover ended up just in
reach of some targets on Kaibab, though apparently not the most desirable
ones. The spacecraft is in good health, and all functionality is
available. This is a 34m Sol, and so the DTE is extremely limited. 4.05
Mbits, minus 2 Mbits for engineering. Not even enough left for one Hazcam
pair. More on that later. The UHF pass was received, and parts of it were
used during sequence development. More on that later as well.
Sol 12 is an IDD Sol:
- It was decided that the potentially accessible targets on Kaibab were
adequate to not require another approach Sol. So Sol 12 is an IDD Sol.
Through the SOWG meeting, the accessibility of the potential targets was
being developed and was not finalized even by the end of the SOWG meeting.
So the SOWG chair had to go to the sequence meeting not knowing what
targets we could get to with what, and so he carefully established
priorities with the science team to be able to make target decisions
during the sequence development process.
- The key activity is to get at least two of CMI, APXS, and Mössbauer on
a target in reach, and furthermore to get enough status in the DTE to
determine that at least two of the measurements were be likely to have
been successful in order to permit a long traverse on Sol 13.
Sequence Development:
- The sequence development for this Sol was, well, interesting. Coming
into the sequence meeting, we had only one target on which we could do
APXS and Mössbauer, but not CMI. This would make it tricky to get
confirmation in the DTE (but perhaps possible if only X-ray were done with
APXS, as was pointed out by Steve later). Despite the failure up to that
point to find a CMI target, the mission manager sent off one sequence
developer (Chris) to find an accessible CMI target and to design that
subsequence, in parallel with the main sequence development. The main
development would plan the two instrument in situ observation, but we
would insert the third (CMI) if available during the development process.
- A large sequence was developed to take sky mini-TES observations,
cloud movies with the Navcam, three different series of IPS measurements
(some that were repeats from a previous Sol), Pancam mosaics of Kaibab and
Bonneville, and the arm deploy with APXS and Mössbauer measurements. Near
the beginning of the sequence development, imagery that was supposed to be
on the DTE was received on UHF that was intended to support the
observation development. The mission manager approved the use of that
imagery to adjust the placement of the Sol 12 observations. Additional
Pancam on Kaibab and Bonneville was added to fill the FIDO time available,
as well as make better use of the UHF.
- Chris succeeded in developing a CMI observation after some contortions
of the arm to avoid hitting the rock. The CMI was on a spot not coincident
but relatively near to where the APXS and Mössbauer measurements were
being taken. The mission manager then sent Ashitey off to verify the
safety of the arm movements designed by Chris. They came back with a
verified plan, and the CMI observation was integrated with the other arm
operations. This sequence was incorporated, but the ordering of it and the
spectroscopy did not permit getting the status on DTE. So Chris was sent
back to reorder the observations: CMI, Mössbauer, and APXS. He came back
with that in time to integrate it into the overall sequence before the
validation phase of the sequence development (see the modified sequence
development schedule in the comments below). It was integrated
successfully. Chris Leger was the hero of this Sol.
- Now we were left with the problem of getting enough information on the
DTE to permit a drive on Sol 13. That information is both Hazcam pairs
from the CMI placement and the Mössbauer placement (two out of three in
situ observations are required for a location). Unfortunately the DTE
volume would not permit even on Hazcam pair, though just barely. The test
director was asked for a ruling to allow more highly compressed Hazcam
pairs to permit fitting both pairs in the limited DTE, which meant more
than a factor of two higher compression from the standard 16:1. It was
asserted and supported that such high compression levels with the ICER
algorithm would permit determining what would be needed to ascertain the
efficacy of the arm operations. The test director permitted the
compression approach (even though the images we will see won't really be
compressed), and the sequence placed both Hazcam pairs on the DTE.
- During the sequence approval phase, it was noted that during the cloud
movie, relative mast movements were being used for the first time. After
some discussion it was realized that the last of a series of relative
moves took the mast to exactly its limit at 270°. While absolute moves to
270° had been done before, relative moves had not and there was some
concern that accumulated error might bust the limit. The consequence would
be a termination of the sequence and no arm activity, since the arm
movements followed the movie. The mission manager requested either a rapid
redesign of the sequence to replace the final movements to 270° with
absolute commands, or if not possible in the time available, to simply
delete the movie sequence. The sequence redesign was accomplished, and
that portion of the sequence was revalidated. The approval meeting then
continued.
- The arm movement near the rock generated considerable discussion, but
the in the end, the mission manager concluded that from previous FIDO
testing and arm software testing, and from the quality of the range data
that was used to plan the arm movements, that the operation was safe. We
will see if the mission manger was right.
- The uplink was approved four minutes before radiation. Fun was had by
all.
Sol 13 Considerations:
- Verify that the two Hazcam image pairs of the CMI and Mössbauer
placements shows proper placement. Based on that (or the lack of it) make
the judgment call that we can or cannot leave Kaibab. Verify that the
Navcams from Sol 11 were received on UHF during Sol 12 to permit the drive
design to Bonneville or to wherever the SOWG decides to head. Make sure
everything is stowed before heading out, of course.
- We have 40m of traverse and one location so far. If the above two
measurements are successful and the data are received (first attempt
during the UHF pass during Sol 13 planning), then we will have two
locations. Trenching is planned for Bonneville, if we go there and if it
turns out to be what they think it is. A really long drive should be
planned after Bonneville if we expect to make the 200m bogie. The system
is capable of up to 100m a Sol over relatively flat terrain. Traverses of
100m to 200m have been suggested by members of the science team, in order
to explore areas that cannot be seen from the lander panorama. This sort
of discussion should be encouraged.
Cumulative Comments:
- One science request was not correctly recorded during the Sol 11 SOWG,
and we instead implemented different version of the observation. This
resulted in too many resources being applied to that observation that
could have been used to do an atmospheric observation that had to be
dropped. The SOWG chair must record and read back the decided upon
observations for confirmation.
- We should note where we actually end up on the approach to adjust
expectation for future approaches. I wonder whether halfway is the right
choice, since there is probably a bias one way or the other based on the
terrain characteristics.
- We have only gone a little over 40m so far. 200m mission success will
not be met without very aggressive driving after Bonneville. We will need
to define a long traverse over terrain so flat and obstacle free that we
can safely turn off hazard avoidance. (This is probably a note for me on
Sols 15-18.)
- We should change the FIDO timeline to document how this seems to be
really working:
Is:
- 15 minute Sequencing Team Meeting
- 60 minute Build and Validate Sequence
- 15 minute Review and Approve Sequence
Should be:
- 70 minute Sequence Design
- 10 minute Sequence Validation
- 10 minute Sequence Approval
In addition, another 30 minutes of meetings follow at least the
morning uplink at 10:30 am:
- SOWG debrief to summarize what they did and didn't get in the
sequence development
- Selection of PIO image or other releases, and assignment to
science team for creation and story writing
- Squyres debrief on science team performance and recommendations
- Three (!) targets were all named "arm8" by different people creating
them. One was later renamed to "arm10\" (the "\" is not my typo). As it
turns out, one of the remaining "arm8" targets was used in the uplinked
sequence. Great care was taken to make sure it was the right arm8, but
this should clearly be avoided if possible.
- When reusing a sequence from a previous Sol, ask if a) the state
before and after the inserted sequence is set properly, b) were there any
errors realized in the old sequence that need to be fixed, and c) were
there any other assumptions about that sequence that need to be rechecked
in the new environment.
- The mission manager forgot to note where the approach on Sol 11 ended
up relative to the midpoint target, as he had recommended. Someone should.
- It seems that this mission manager likes to refer to himself in the
third person.
|